Hyundai Automobile Factory - St.Petersburg   2008-2009:

Pulkovo Airport New Terminal Building, St.Petersburg 2011-2012:

Alfa Construction, as a sub-contractor of Reinforced Concrete Works, finished the project in 8 months. Client: Amco Hyundai Corp. General Contractor: Renaissance Construction Total area: 100000 sqm.

Alfa Construction, as a sub-contractor of Reinforced Concrete Works, finished the project in 8 months. Client: Amco Hyundai Corp. General Contractor: Renaissance Construction Total area: 100000 sqm.

1/6

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works. The project is finished. Client: Northern Capital Gateway LLC, Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 40000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works. The project is finished. Client: Northern Capital Gateway LLC, Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 40000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/20

Pulkovo Airport Nord Pier Building, St.Petersburg 2012-2013 :

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works. The project was handed over Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 9000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works. The project was handed over Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 9000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/6

Pulkovo Airport Carpark Building, St.Petersburg 2012-2013 :

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works. The project was handed over. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 15000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works. The project was handed over. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 15000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/6

Pulkovo Airport GSE Building, St.Petersburg 2012-2013 :

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works. The project was handed over. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2300 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works. The project was handed over. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2300 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/5

Pulkovo Airport Main Water Reservoir Building 2012-2013 :

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works. The project was handed over. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2900 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works. The project was handed over. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2900 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/6

Pulkovo Airport 400Hz  Lines Infrastructure Works 2012-2014 :

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works which include channels, pits, electrical lines fixing etc. The project is ongoing. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 150000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works which include channels, pits, electrical lines fixing etc. The project is ongoing. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 150000 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/3

Pulkovo Airport De-icing Buildings 2013-2014 :

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works( 2 Buildings). Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2600 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works( 2 Buildings). Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2600 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works( 2 Buildings). Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2600 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/3

Pulkovo Airport ESTOP Building 2013-​2014 :

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2300 sq m. Address: Pulkovo 1 Airport, St. Petersburg

Alfa Construction has signed the "turn key" contract as a Main Contractor of the Works. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 2300 sq m. Address: Pulkovo 1 Airport, St. Petersburg

1/3

Pulkovo Airport Fixed Link Rotunda  and Electrical Houses 2014-2015 :

Alfa Construction has signed the contract as a Contractor of Reinforced Concrete Works. Client: Ictas-Astaldi General Contractor: IC-Ictas Astaldi, St. Petersburg Total area: 4100 sq m. Address: Pulkovo 1 Airport, St. Petersburg